SoftBank's AI data-center and power developer filed for a Nasdaq listing under ticker SBE in September 2026. Nvidia and OpenAI are both investors and customers, and six weeks later the offering still hasn't priced.

VC
Editor-in-chief: Trace Cohen โ€” Angel investor, VC, family office, operator and founder ยท 3x founder (BrandYourself, Launch.it, SPOT) ยท 65+ investments

AI-assisted: drafted with AI from the cited sources โ€” how we check it

65+Investments3xFounder$200M+Funds Tracked

Quick Answer

SB Energy, SoftBank's AI data-center and power developer, filed to list on the Nasdaq under ticker SBE, targeting a roughly $50 billion valuation and a $5-7 billion raise, according to Bloomberg and CNBC. As of its most recent S-1/A on September 21, 2026, the IPO hadn't priced, and the company's data centers generate no revenue yet against a $439 billion contracted backlog.

SB Energy, SoftBank's AI data-center and power developer, is targeting a roughly $50 billion valuation and a $5-7 billion raise in its Nasdaq IPO under ticker SBE โ€” but six weeks after its last SEC amendment, the offering still hasn't priced.

SB Energy publicly filed a Form S-1 with the SEC on September 1, 2026, and has applied to list on the Nasdaq Global Select Market and Nasdaq Texas. The company combines gigawatt-scale AI data-center development with the solar, battery and gas generation that powers it โ€” and its two biggest backers, Nvidia and OpenAI, are also two of its biggest customers.

SB Energy IPO: backlog, valuation target, and Nvidia/OpenAI ties
$50B+
per Bloomberg, CNBC
Target valuation
$5-7B
per Bloomberg, CNBC
Target raise
$439B
SEC S-1, Sept 2026
Contracted backlog
$3B
+$105B build guarantee
Nvidia commitment

Figures from SB Energy's S-1 filings (SEC EDGAR) and Bloomberg/CNBC reporting, September 2026.

SB Energy IPO: Target Valuation, Raise, and Terms

SB Energy's own S-1 left the share count and price range blank โ€” standard for an initial filing โ€” but Bloomberg and CNBC both reported the company is seeking $5 billion to $7 billion in the offering at a valuation around $50 billion. J.P. Morgan, Goldman Sachs, Morgan Stanley, Citigroup and Mizuho are the joint lead book-running managers, according to SB Energy's own September 1, 2026 press release.

MetricDetail
Exchange / TickerNasdaq Global Select Market & Nasdaq Texas: SBE
Original S-1 filedSeptember 1, 2026
Amendments filedSeptember 4 and September 21, 2026
Target raise$5B-$7B (Bloomberg, CNBC)
Target valuation~$50B (Bloomberg, CNBC)
Contracted backlog~$439B ($430B data centers, $10B power)
Contracted/under-construction capacity8.8 GW
Revenue (TTM to June 30, 2026)$268.84M
Net loss (TTM to June 30, 2026)$7.01B
Operational data centersNone
Lead book-runnersJ.P. Morgan, Goldman Sachs, Morgan Stanley, Citigroup, Mizuho

How we counted: figures from SB Energy's S-1 and S-1/A filings (SEC EDGAR) and Bloomberg/CNBC reporting on deal terms; as of the September 21, 2026 amendment.

A $439 Billion Backlog Against Zero Operating Revenue

SB Energy's S-1 reports roughly $439 billion of contracted backlog โ€” about $430 billion in data-center commitments and $10 billion in standalone power โ€” across 8.8 gigawatts of capacity contracted or under construction in Texas and Ohio, according to Yahoo Finance's reporting on the filing. None of that capacity is operational yet: about 803 megawatts-IT is under construction in Texas, the Ohio campus's first phase targets 2028, and later buildings are slated for 2031 and 2032.

Backlog of this kind is the undiscounted sum of what customers would pay if every campus gets built, energized and operated for the full multi-decade contract term โ€” not bookings that convert next quarter. Against that $439 billion figure, SB Energy reported revenue of $268.84 million and a net loss of $7.01 billion for the twelve months ended June 30, 2026, per the company's amended S-1 on SEC EDGAR. The company also carries roughly $3.8 billion in accumulated deficit and about $4 billion of debt, per Yahoo Finance's review of the filing. SB Energy's own S-1 states it will "require significant additional capital to construct and complete certain of our projects."

Why Nvidia and OpenAI Are Both Investors and Customers

Nvidia has committed $3 billion total to SB Energy's offering: a $1.5 billion prepaid forward contract and a $1.5 billion private placement of newly issued, non-voting Class N shares, both priced at 90% of the public offering price, according to Bloomberg's September 21, 2026 report on the filing. Separately, Nvidia has guaranteed up to $105 billion tied to the initial 4.25 gigawatt-IT Ohio phase, with an option to guarantee the remaining 3.78 gigawatts-IT, per the S-1 as reported by Yahoo Finance.

OpenAI is SB Energy's anchor tenant, having signed 20-year leases covering roughly 8.0 gigawatts-IT across 17 buildings at the Ohio PORTS-Pike campus specifically built to supply its AI compute. SB Energy's own S-1 discloses that the company is "substantially dependent" on OpenAI as a customer. That structure โ€” Nvidia financing the power infrastructure behind a major GPU customer, while SoftBank separately invests tens of billions in that same customer โ€” means supplier, investor and tenant overlap across the deal in ways that make SB Energy's revenue quality hard to assess independent of its counterparties' own financial health.

What the headline misses

A $50 billion valuation target and a $439 billion backlog describe a company that is, by its own numbers, pre-revenue on the business the IPO is actually selling: none of SB Energy's data centers are energized, and the $268.84 million it has booked over the past year comes almost entirely from legacy power operations, not AI hosting. The circular financing โ€” Nvidia as investor, guarantor and GPU supplier; OpenAI as tenant while SoftBank separately bankrolls OpenAI elsewhere โ€” means a stumble at any one of the three companies shows up on all of their balance sheets at once. And six weeks after its most recent amendment, SB Energy hasn't even set a price range, which is itself a signal that the roadshow Bloomberg described in September hasn't converted into investor demand on the timeline the company hoped for.

Bottom line: SB Energy is asking public investors to price a $50 billion AI infrastructure bet on a $439 billion backlog that's still almost entirely unbuilt, backed by Nvidia and OpenAI โ€” who are also its biggest counterparties. The company hadn't set a price range as of its September 21, 2026 amendment, and the real test is whether energized megawatts, not backlog dollars, start showing up on schedule once the offering actually prices.

Track SB Energy and the rest of the 2026 pipeline on the Tech IPO Tracker.

Get VC data most people never see

โ€” free to subscribe

Trace's notes on venture, AI and startups, a few times a week. Join 5,000+ subscribers. No spam.

No spam, unsubscribe anytime. Sent via Substack ยท Privacy ยท or subscribe on Substack โ†—

Frequently Asked Questions

What valuation is SB Energy targeting in its IPO?

SB Energy is targeting a valuation of roughly $50 billion and aims to raise $5 billion to $7 billion, according to Bloomberg and CNBC reporting on the company's IPO plans. SB Energy itself has not disclosed a share count or price range in its public filings, so these figures come from reporting on the deal rather than the S-1's own terms.

Has SB Energy's IPO priced yet?

No. As of SB Energy's most recent amended registration statement, filed September 21, 2026, the SEC EDGAR filing history shows no pricing has been set. Bloomberg reported on September 22, 2026 that the company planned to begin IPO marketing once SEC review concluded, but no roadshow completion, price range, or trading date had been reported as of October 14, 2026.

How big is SB Energy's contracted backlog, and how real is it?

SB Energy reports a contracted backlog of about $439 billion, including roughly $430 billion in data-center commitments and $10 billion in standalone power, per the company's S-1 as reported by Yahoo Finance. That figure is the undiscounted sum of multi-decade customer contracts if every campus is built and energized on schedule โ€” not booked revenue, and none of it is reflected in the company's current financials.

Why is Nvidia investing $3 billion in SB Energy's IPO?

Nvidia has committed $3 billion total to SB Energy's offering โ€” a $1.5 billion prepaid forward contract and a $1.5 billion private placement of non-voting Class N shares, both priced at 90% of the IPO offering price, according to Bloomberg's reporting on the September 21, 2026 S-1 amendment. Nvidia has separately guaranteed up to $105 billion tied to construction of the initial Ohio data-center phase, per SB Energy's S-1 as reported by Yahoo Finance.

What is SB Energy's relationship with OpenAI?

OpenAI is SB Energy's anchor tenant, having signed 20-year leases covering about 8.0 gigawatts of IT capacity across 17 buildings at the Ohio PORTS-Pike campus, per SB Energy's S-1 as reported by Yahoo Finance. SB Energy's own filing states the company is "substantially dependent" on OpenAI as a customer, even as OpenAI and SoftBank are separately intertwined through billions of dollars in other investments.