Analysis
As of November 16, 2026, Blackstone Digital Infrastructure Trust (NYSE: BXDC) has agreed to buy a controlling stake in two Amazon Web Services data center joint ventures in a transaction valued at about $5 billion, the trust said in a press release filed with the SEC. The trust's Form 8-K puts the aggregate gross value at $5.0 billion and the initial capitalization rate at 7.0%. The portfolio is 13 newly constructed data centers with 647 megawatts of capacity: nine buildings on a campus in northern Indiana and four on a campus in Mississippi. BXDC will hold a 75.1% controlling interest in each joint venture, and AWS keeps the rest.
AWS will lease back 100% of the buildings on a triple-net basis, with a weighted average initial lease term of 12 years and a fully extended term of 32 years, per the 8-K. The contribution agreement was signed on November 11, 2026, and the deal is expected to close in the fourth quarter of 2026, subject to closing conditions. A breach entitles the other side to a termination fee of $150.0 million.
What does Blackstone Digital Infrastructure Trust do?
BXDC is a real estate investment trust externally managed by Blackstone, built to acquire and own data center assets. Its chief executive and president is Nick Pell, who said in the release that the assets' quality, basis and tenant profile make them an attractive match for the deployment of the trust's IPO proceeds. This is the trust's first investment. Prasad Kalyanaraman, AWS's vice president of infrastructure, was the Amazon executive quoted.
“The contribution agreement was signed on November 11, 2026, and the deal is expected to close in the fourth quarter of 2026, subject to closing conditions.”
BXDC IPO and how the $5B deal is funded
The trust's initial public offering was 87.5 million shares at $20.00 each, with trading on the New York Stock Exchange set to begin on May 14, 2026, as reported by StorageNewsletter, which by our arithmetic is $1.75 billion before any underwriter option.
That equity alone does not cover a $5.0 billion portfolio. The 8-K says the purchase is expected to be funded with the net proceeds of about $2.5 billion of new non-recourse mortgage loans, so roughly half the gross value is debt secured on the buildings themselves. BXDC shares rose 6.7% on Monday, Investing.com reported.
Morgan Stanley, CBRE Capital Markets, Citi, Goldman Sachs, J.P. Morgan and Wells Fargo Bank advised on the deal, and Simpson Thacher & Bartlett was legal advisor to Blackstone.
Value Add VC data
- May 2026, IPO -- 87.5 million shares at $20.00 per share, NYSE ticker BXDC (StorageNewsletter)
- Nov 2026, first acquisition -- 75.1% of two AWS joint ventures at a $5.0B gross value and a 7.0% initial cap rate (SEC 8-K)
Our arithmetic on the filed figures: $5.0 billion across 647 megawatts is about $7.7 million of gross value per megawatt, and a 7.0% cap rate implies about $350 million of first-year net operating income on the full portfolio.
Blackstone's data center deals and comparables
- QTS -- bought by Blackstone in 2021 for about $10 billion including debt, as reported by The Next Web.
- AirTrunk -- Blackstone's 2024 deal valued the Australian operator at A$24 billion ($16.1 billion), per Data Center Knowledge; AirTrunk runs data centers in Australia, Singapore, Hong Kong, Japan and Malaysia.
Against those platform deals, the AWS portfolio is a different product: no operating company, no development pipeline, just finished buildings and one tenant's rent. Pulse has tracked Blackstone's run of infrastructure bets and Amazon's AI spending, and this deal connects the two: the cloud builder supplies the buildings, the private-capital firm supplies the balance sheet.
The risks in a single-tenant $5B portfolio
The headline number is announced, not closed. The 8-K says the transactions are subject to conditions and may not be completed on their contemplated terms. Even after closing, every dollar of rent comes from one tenant across two campuses, and the initial lease runs 12 years on buildings designed for today's chips and cooling. The 32-year figure assumes AWS exercises every extension. BXDC's equity holders also sit behind about $2.5 billion of mortgage debt, which magnifies both the 7.0% yield and any re-leasing risk at the end of the initial term. In our view, northern Indiana and Mississippi would be harder places to re-lease a vacated building than a dense data center hub.