Is this your company? Get featured or correct your listing →
Latest Pulse
- Aug 5, 2026Samsung Will Build Floating Data Centers Off HoustonSamsung Heavy Industries signed an engineering contract with Mousterian to build barge-mounted data centers of 50MW each, sited in Houston next to a gas plant and cooled without potable water, targeting 2028.→
- Aug 4, 2026Texas Halts New Data Center Grid ConnectionsGovernor Greg Abbott ordered a pause on new data center connections to the Texas power grid after ERCOT found pending requests -- roughly 90% from data centers -- totaled about 474 gigawatts, five times the state's peak recorded demand.→