Amazon Backs 12 New Nuclear Reactors In Indiana

Amazon will fund and be the first buyer of power from a proposed 960-megawatt nuclear plant in Indiana built with 12 of X-energy's small modular reactors, its second and much larger deal with the reactor maker.

By the Numbers

960 MW
Planned plant capacity
12 Xe-100 units
Small modular reactors
$700M Series C-1
Amazon's 2024 X-energy round
~3x larger
Scale vs. 2024 deal
5 GW
Industry 2039 nuclear capacity goal
Amazon Backs 12 New Nuclear Reactors In Indiana: key figures
ShareXLinkedInEmail

THE RUNDOWN

1

This is roughly three times the size of Amazon's first X-energy deal from 2024, showing hyperscalers are scaling up nuclear commitments even though no small modular reactor has yet been built and connected to the U.S. grid at commercial scale.

2

The plant would feed the public grid with Amazon as first buyer -- a structure that spreads power-procurement risk across ratepayers and Amazon rather than Amazon building fully dedicated behind-the-meter capacity.

3

X-energy's own flagship project at Dow's Seadrift site in Texas hasn't broken ground and is tied up in a lawsuit alleging regulatory non-compliance, meaning the technology underlying Amazon's bigger Indiana bet is still unproven at commercial scale.

4

X-energy's stock is down nearly two-thirds from its post-IPO high despite the news, a reminder that public markets are pricing SMR execution risk far more conservatively than hyperscaler procurement announcements suggest.

The VC Read

Value Add VC analysis

The diligence item here isn't the megawatts, it's the sequencing: Amazon is now committed to a second, three-times-larger X-energy deal before the company's first flagship project in Texas has broken ground or fully cleared its NRC permit, and that project is in active litigation. Watch Seadrift's permitting timeline, not the Indiana press release, for the real signal on whether X-energy's SMR technology ships on anything like the schedule hyperscalers are implying.

Analysis

Amazon will fund development of a proposed 960-megawatt nuclear plant at a demolished coal-plant site south of Terre Haute, Indiana, and will be the first buyer of its power, the company and reactor maker X-energy said Monday, according to TechCrunch. The plant would use 12 of X-energy's Xe-100 small modular reactors, with American Electric Power operating the facility.

It's Amazon's second commercial agreement with X-energy and roughly three times the size of its first, a deal built on top of Amazon's lead role in X-energy's $700 million Series C-1 round in 2024. The power would feed the public grid, with Amazon as the anchor buyer -- the company says it would also serve its own data centers, though Monday's announcement stopped short of framing the deal explicitly as an AI-power play, instead pitching small modular reactors as a way to revive an industry that has struggled for decades with cost overruns and construction delays.

“nuclear capacity by 2039, a goal that depends on X-energy first successfully delivering its flagship project at Dow Chemical's Seadrift site in Texas.”

The companies are aiming for 5 gigawatts of new U.S. nuclear capacity by 2039, a goal that depends on X-energy first successfully delivering its flagship project at Dow Chemical's Seadrift site in Texas. That project hasn't broken ground: its construction permit is in the final phases of Nuclear Regulatory Commission review, and the site is tied up in a Texas lawsuit alleging "habitual non-compliance" with water and waste regulations. Mass manufacturing of SMR components is supposed to eventually lower costs industry-wide, but the benefits of that scale are likely a decade away even in optimistic timelines.

Markets read the announcement cautiously: X-energy shares, which IPO'd in April at $23 and have since fallen nearly two-thirds from their post-debut high, rose about 10% in pre-market trading on the Indiana news but gave back most of that, trading down less than 2% once the news was fully priced in. That gap between hyperscaler enthusiasm and public-market skepticism is the clearest signal in the story: Amazon is willing to commit capital and offtake years ahead of any reactor actually generating power, while investors who can trade X-energy daily are pricing in real execution risk.

Seadrift, not Indiana, is the real signal to track -- until X-energy's first flagship reactor clears its NRC permit and breaks ground in Texas, every subsequent deal, however much larger, is a bet on a timeline nobody has yet proven out.

ShareXLinkedInEmail

Key Sources

1 source

Reported by TechCrunch · Analysis by Value Add Pulse.